NEW ALBANY, Ohio (WCMH) -- This was the year of the super load, with more than two dozen enormous transports crossing county lines to reach growing tech facilities, particularly New Albany's Intel plant.
Initially announced as just under two dozen super loads, 2024 ended up seeing 32 of the massive transports, starting in March and continuing through December. In total, more than 11 million pounds of goods were transported.
Each super load began its journey into Ohio the same way...