QUETTA: A special audit report has revealed irregularities of Rs2.4 billion and delays in the construction of 100 dams in Balochistan.
It added that work on 26 out of 100 dams was completed in 2021 instead of 2018. The delay ballooned construction costs by Rs261 million.
Expenses of the project implementation unit and supervision also went up by Rs133.6m, the report added.
An additional payment of Rs112.6m was made to non-shareholders while contractors were charged Rs9.9m...